WP4: provide parallel processing power to ASTRO-WISE
Objectives:
- provide the necessary computing power to the prime data centres
- install and operate Linux-Beowulf 32 Gigabit PC parallel clusters
Work description:
- hardware procurement and installation
- upgrading and export to other main sites of existing 4 PC clusters
- maintenance
Planned total man month over 4 years (from contract)
NOVA |
|
ESO |
|
OAC |
|
TERAPIX |
|
USM |
|
Begeman |
12 |
Slijkhuis |
6 |
Getman |
1 |
Missonnier |
7 |
EC- Snigula |
3 |
Deul |
4 |
|
|
Grado |
6 |
|
|
Gabler |
4 |
|
|
|
|
Pavlov |
7 |
|
|
|
|
|
|
|
|
EC-Volpicelli |
4 |
|
|
|
|
Total |
16 |
|
6 |
|
18 |
|
7 |
|
7 |
WP 4 |
54 |
|
|
|
|
|
|
|
|
MILESTONES
Phase I: be ready to receive first data without later redefinition
or re-shuffling - 2002
- T0 kick-off- prepare design review for WP4
- T0 + 2Q procure hardware, start sub-component installation
- T0 + 3Q deliverable: first version of operational
(smaller) cluster
Phase II: evaluate and prepare for mass production -2003 -2004
- T0 + 9Q Upgrade hardware- ready for bulk operations
- T0 + 10Q System full mass production proof
Phase III: qualify, operate and populate the mass production system
-2005
- T0 + 11Q Review and set goals of final delivery system
T0 + 15Q deliverable: operational parallel clusters at partner
centers