The ASTRO-WISE programme is split into 6 workpackages:
The WP pages are used to list ACTION ITEMS, persons involved, and monitoring the progress on the action items.
During contract negotiations the following distribution of workload over
packages and partners was layed out (numbers represent man month)
NOVA | ESO | OAC | IAC |
USM | VISTA | TOTAL | |
WP1 | 41 | 30 | 33 | 28 | 20 | 152 | |
WP2 | 74 | 66 |
27 | 36 | 24 | 227 | |
WP3 | 52 | 24 |
18 | 33 | 3 | 130 | |
WP4 | 16 | 6 | 18 | 7 | 7 | 54 |
|
WP5 | 9 | 6 | 10 |
7 | 6 | 38 |
|
WP6 | 28 | 8 | 12 | 10 | 8 | 22 | 88 |
coordination adm. | 12 | 12 | |||||
reserved | 12 | 12 | |||||
TOTAL | 220+24 | 140 | 118 | 121 | 68 | 22 | 713 = 59 fte |
Notes:
--for Terapix numbers are according internal arrangements; differing
from contract forms due to different cost modelling
-- Grado moved 10 month from WP5 to WP4 due to error in contract
forms (Nov 2001)
-- ESO NN 6 month moved from WP2 to WP3 (December 2001).
-- OAC: finetuned with two new Astro-wise persons WP1:33->30, WP4
17->16, WP5 4->8 (January 2002)